Vejdirektoratet says the planned third Limfjord crossing west of Aalborg will cost about 3.5 billion kroner more than budgeted, and its project chief doubts the 2035 opening can be kept.
The Danish Road Directorate, Vejdirektoratet, has told politicians at Christiansborg that the original project has grown 3.5 billion kroner more expensive. DR reports that it is now up to parliament to decide what happens next.
The Folketing set aside around nine billion kroner for the North Jutland motorway project in 2024. According to Nordjyske, the new calculations put the total at roughly 12.5 billion kroner. Kristeligt Dagblad describes the increase as about 40 percent.
PFAS, soft ground and concrete prices behind the overrun
Mette Bentzen, project chief at Vejdirektoratet, told DR that prices for concrete and gravel have risen, much as they have in supermarkets. She added that more PFAS contamination has been found in the area, and that removing it will be very expensive. The soil conditions are also worse than expected, which makes construction harder.
Nordjyske breaks the figures down further. Environmental requirements tied to the PFAS-contaminated sludge depot at Mølholm, including replacement nature, account for about 700 million kroner. Difficult soil conditions add 900 million to 1.3 billion kroner, while materials and tunnel components add 1.7 billion kroner.
Nordjyske notes that all the figures are preliminary and still under review. Ingeniøren, which calls the overrun a price explosion, confirms that Vejdirektoratet published the numbers on Tuesday. As reported by TV2 Nord, the Environmental Protection Agency, Miljøstyrelsen, has said the PFAS waste disposal strategy in the application is still missing information.
A bridge instead of a tunnel is one of the options
Vejdirektoratet has also drawn up proposals that could cut costs. One option is a bridge instead of a tunnel south of the island of Egholm. Nordjyske reports that a bridge could cover most of the extra cost, while TV2 Nord has cited bridge options worth up to 2.7 billion kroner in savings.
According to Mig og Aalborg, the savings catalogue also includes a cut-and-cover tunnel and a motorway without hard shoulders, and about 900 million kroner in savings within the sunken tunnel design itself. No alternative has been chosen.
Bentzen told DR that it is hard to see the project finishing on time if the pace is slowed now. Kristeligt Dagblad reports that the solution options are expected to reach the political agreement circle during 2027. The other outlets found do not confirm a delay, and state only that the schedule is at risk.
What the delay risk means for internationals driving in North Jutland
The third Limfjord crossing was approved by the Folketing through bill L 112, recorded by Folketingstidende as a four-lane motorway west of Aalborg via Egholm, to be built by 2034. DR’s reporting refers to a 2035 opening. Vejdirektoratet is the state road authority that plans and builds motorways, and the final call on scope and funding sits with politicians, not the agency.
For foreign residents who commute across the fjord, nothing changes on the road today, and no new opening date has been announced. If you are weighing the long-term cost of driving in Denmark, including the total cost of owning a car, the sourced facts are these. Vejdirektoratet’s figures are preliminary, a bridge or a scaled-back tunnel is on the table, and the decision is expected to move to the political agreement circle during 2027, per Kristeligt Dagblad.