Three North Zealand municipalities are moving ahead with the Nordkystens Fremtid coastal protection project after 13 years of discussion, with Gribskov’s council expected to approve it on September 8, 2026.
DR reports that Gribskov, Halsnæs and Helsingør have finally found solutions to the disputes that repeatedly stalled the plan. According to DR, politicians in Gribskov are expected to vote yes on Tuesday, clearing the way for construction.
The project involves establishing a stone reef off the North Zealand coast. In addition, 36 kilometers of the 57 kilometer shoreline will be sand fed. DR links the plan to storm surge and erosion risk along the coast.
The scheme has been on the drawing board for 13 years. As reported by DR, price rises, environmental concerns and disagreement over who should pay have paused the work several times. That left doubt about whether the coastal protection would ever be built.
Financing has been the main obstacle. Per DR, the most recent report, from 2024, put the total cost at more than 900 million kroner, of which 86.7 million kroner would come from the state. The remainder falls on the three municipalities and local property owners.
Mayor points to municipal budgets
Trine Egetved (C) is mayor of Gribskov Municipality. She told DR that she fundamentally sees the coast as a state task rather than a municipal one. The municipality is nevertheless taking its share of the bill and lifting the task, she said.
Egetved also pointed to the consequences for other local spending. According to her account to DR, the municipality will be under pressure in the coming years. Fewer bike paths can be built, and fewer daycare centers and schools can be renovated.
Summer house owners await the sand
Birgit Lund owns a summer house at Vejby in Gribskov Municipality. She chairs Samvirket af Nordsjællandske Dige og Kystsikringslaug and has followed the case for years. She described the prospect of construction as a relief, DR reports.
Lund is not fully convinced that her coastal property is safe yet. As stated to DR, she will not have peace of mind until the sand is actually on the beach. The sand feeding is the element most directly aimed at protecting the shoreline.
The decision in Gribskov is not the last step. DR notes that Halsnæs and Helsingør municipalities are also expected to vote yes at their coming council meetings. Approval by all three is required for the project to start.